Estimating Activity Costs And Developing Budget For Case Project

Answer:
Project Activities
Activity List:
WBS
Task Name
Duration
Start
Finish
0
Essendon & Buckley Street level crossing removal
985 days
Wed 4/25/18
Tue 2/1/22
1
Initiation phase of the project
73 days
Wed 4/25/18
Fri 8/3/18
1.1
Identifying objectives of the project
15 days
Wed 4/25/18
Tue 5/15/18
1.2
Undertak